PROJECT NAME: ONLINE CHECKING CODE NO @ IIUM PHOTOCOPHY

Activity

Precedence

Duration (days)

A

2

A : Create used interface Mock-ups

B

2

B : Conduct design review

C

A

3

C : Obtain user signoff

D

B

4

D : Develop technical specification

E

5

E : Determine data import/export elements

F

C

5

F : Define user needs

G

D

4

G : Define IT needs

H

G,E

3

H : Design interfaces

I

F

2

I : Determine vendor

J

H,I

1

J : Monitor the vendor


Table 1: Network Diagram Data for Web Site Design Activity























Figure 1-1. Activity-on-Arrow (AOA) Network for Web Based Checking Code(refer to hard copy)


  1. Path 1 : A-C-F-I-J Length = 2+3+5+2+1 = 13 days

    Path 2 : B-D-G-H-J Length = 2+4+4=3+1 = 14 days

    Path 3 : E-H-J Length = 5+3+1 = 9 days


  2. The critical path for this group is Path 2, B-D-G-H-J and it takes 14 days.


  3. The shortest possible time it will take to complete this group of activities is 14 days.


  1. The slack time for Path 3 :E-H-J in the network diagram which is not the critical path.


    0 2 2 5 5 10 10 12




0 2 2 5 5 10 10 12

0 2 2 6 6 10 10 13 21 22




8 10 10 14 14 18 18 21 21 22


0 5




6 11


(this figure refer to hard copy)

  1. Slack time E = 11-5

    = 6 days


  2. Slack time H = 21-13

    = 8 days


  3. Slack time J = 22-22

    = 0 days