IT Project Management Class taught me a lot of information on project management. In this class also, it as an effort to educate me, tomorrow's project managers, about what will help make a project succeed and what can make it fail. In addition, this class provides practical lessons in project management for students like me. What I like best about this course is because of the lecturer. The lecturer named is Mdm. Masita Abdul Rahman. For me, how to make the class interesting is look at the approach that lecturer teach and how to interact with the student proficiently. In my observation, she tries her best in order to make the class more attractive and interesting. At the same time, we all can get the benefit from this class as well as we can apply it in one day, insyaAllah. What I dislike about the course is need to read a lot. I found myself always read books passively and recklessly. When I have to read textbooks, this will happen easily. Some contents of those textbooks are quite long and boring. Also, I need read the whole chapter to get more information and concepts about this subject. But I do not think it is easy to read. In my suggestion, I proposed to the lecturer to expose the students with the real project management. What I mean here, we need to be exposed by the real project management in order to understand what is the exactly happen in project management. Moreover, I proposed that from the lecturer to make many activities in the class that related to this subject. I am also wanted to suggest that we can make this class in other place. It means that, we can have a class in outside environment instead being in class all the time. So, it will be more relax and the students not feel boring. If I had more time, I wish to do give more information on this course to all my classmates and sharing with them that I have and the lecturer as well, insyaAllah.
ASSIGNMENT 2 | 9:00 PM |
Filed under:
|
PROJECT NAME: ONLINE CHECKING CODE NO @ IIUM PHOTOCOPHY Activity Precedence Duration (days) A 2 A : Create used interface Mock-ups B 2 B : Conduct design review C A 3 C : Obtain user signoff D B 4 D : Develop technical specification E 5 E : Determine data import/export elements F C 5 F : Define user needs G D 4 G : Define IT needs H G,E 3 H : Design interfaces I F 2 I : Determine vendor J H,I 1 J : Monitor the vendor Table 1: Network Diagram Data for Web Site Design Activity Figure 1-1. Activity-on-Arrow (AOA) Network for Web Based Checking Code(refer to hard copy) Path 2 : B-D-G-H-J Length = 2+4+4=3+1 = 14 days Path 3 : E-H-J Length = 5+3+1 = 9 days 0 2 2 5 5 10 10 12 0 2 2 5 5 10 10 12 0 2 2 6 6 10 10 13 21 22 8 10 10 14 14 18 18 21 21 22 0 5 6 11 (this figure refer to hard copy) = 6 days = 8 days = 0 days
ASSIGNMENT 1 | 8:58 PM |
Filed under:
|
Business issue Technology issue Organizational issue Figure 2.1: The business, technology and organizational issues(refer to hard copy) Functional Figure 5.1: The functional organizational structure(refer to hard copy) Project Figure 5.2: The project organizational structure (refer to hard copy) Matrix Figure 5.3: The matrix organizational structure(refer to hard copy) The examples to illustrate the importance based on an already implemented project are the KTMB@OnePay. PROJECT MANAGER EXAMPLES Need adequate resources Get approval for unique project needs in a timely manner Receive cooperation from people throughout the organization Need someone to mentor and lead them on leadership issues Table 6.1: Important based on KTMB@OnePay
The business sphere requires a project to concern the cost to the user. It also includes supporting the cost and the impact to the implementation. In technological sphere, it needs to know how each and every tool and technology work. It also needs to know the strengths, benefits, limitations and costs.
In organizational issues, it more concern about the affect of the project to the user.
project. This project has 2 phases to be implemented and Information Technology Division (ITD) was in charge of the project implementation and management. Phase 1 of the IIUM Campus Wide Wireless project was rolled out in February 2008, and was officially launched in May 2008. It was covered the entire academic area at Gombak Campus, Indera Mahkota Campus and Jln Hospital Campus.
While, Phase 2 of the IIUM Campus Wide Wireless project is still ongoing project and expected will fully deployed by end of February 2010. The business, technology and organizational issues that I think can be addressed for the project as follows:-